2-126-1-L
Final inspection Sample dataCrew berthing, starboard side
Closeout checklist
11 of 12 complete- Old fixtures removedOct 7
- Foundations installed, welds inspectedOct 12
- Cables pulled and securedOct 15
- Cables terminated and testedOct 18
- Lighting installed and testedOct 19
- Berths and lockers installedOct 21
- Ventilation reconnectedOct 22
- Penetrations sealedOct 22
- Deck covering installedOct 23
- Paint and labels completeOct 24
- Space cleaned for inspectionOct 26
- Weaver Maritime Technologies QA inspectionToday
Your inspection
Once Weaver Maritime Technologies QA passes this space, you can walk it and sign off here. We will email you the moment it is ready.
Quality evidence
- Weld inspection recordOct 12
- Cable test resultsOct 18
- Lighting test recordOct 19
- Progress photos, 14Oct 26
Records are held in an approved system for controlled information and open there after you sign in.
History
- Moved to final inspectionToday, 10:42, QA inspector
- Space cleaned and ready for inspectionOct 26, 15:10, day shift lead
- Paint and labels completeOct 24, 14:05, day shift lead
- QR code posted, work startedOct 6, 07:30, project lead
Status summaries only. Drawings and controlled records stay in the approved system for controlled information.