Weaver Maritime Technologies

2-126-1-L

Final inspection Sample data

Crew berthing, starboard side

Back to closeout map
Deck and frame
Deck 2, frame 126
Alteration
ALT-104
Work started
Oct 6
Planned closeout
Oct 28
Open items
None

Closeout checklist

11 of 12 complete
  1. Old fixtures removedOct 7
  2. Foundations installed, welds inspectedOct 12
  3. Cables pulled and securedOct 15
  4. Cables terminated and testedOct 18
  5. Lighting installed and testedOct 19
  6. Berths and lockers installedOct 21
  7. Ventilation reconnectedOct 22
  8. Penetrations sealedOct 22
  9. Deck covering installedOct 23
  10. Paint and labels completeOct 24
  11. Space cleaned for inspectionOct 26
  12. Weaver Maritime Technologies QA inspectionToday

Your inspection

Once Weaver Maritime Technologies QA passes this space, you can walk it and sign off here. We will email you the moment it is ready.

Schedule your walkthrough

Quality evidence

  • Weld inspection recordOct 12
  • Cable test resultsOct 18
  • Lighting test recordOct 19
  • Progress photos, 14Oct 26

Records are held in an approved system for controlled information and open there after you sign in.

History

  1. Moved to final inspectionToday, 10:42, QA inspector
  2. Space cleaned and ready for inspectionOct 26, 15:10, day shift lead
  3. Paint and labels completeOct 24, 14:05, day shift lead
  4. QR code posted, work startedOct 6, 07:30, project lead

Status summaries only. Drawings and controlled records stay in the approved system for controlled information.